Guide
How construction draws work.
A construction loan is not advanced at once. It arrives in draws, each one against work that has been checked. This guide explains how that generally works, using Ontario as the example where provincial law matters.
On this page
Money in stages
A lender funds construction as the building goes up, not before. Each advance, or draw, pays for work already in place. The lender needs to know three things each time: what has been built, what it cost, and whether the money left will finish the job.
Many lenders advance on a regular cycle, often monthly, though the loan agreement sets the actual terms. The paperwork is much the same each time, which is why a disciplined first draw makes the rest easier.
One draw, start to finish
- 01
The draw request
The builder and borrower prepare the request: work completed, costs incurred and an updated budget with the cost to complete.
- 02
The cost consultant’s review
The lender’s cost consultant visits the site and reports on progress, costs to date and the cost to complete. The report is what the lender relies on.
- 03
The statutory declaration
The builder swears a statutory declaration, typically confirming that trades and suppliers have been paid for work covered by earlier draws.
- 04
Title and lien search
Before each advance, the lender’s lawyer searches title for registered liens and other new charges.
- 05
The advance
If the report, declaration and search are in order, the lender advances funds, less any holdback that applies.
Cost to complete
The most important number in a draw is not the amount requested. It is the cost to complete. If the cost to finish the building exceeds the undrawn loan plus remaining equity, lenders commonly expect the borrower to cover the difference before further advances.
That is why budget variances matter early. A variance explained early is a conversation. The same variance found late is a problem.
Holdbacks: Ontario as an example
Each province sets its own holdback and lien rules. Ontario’s are a useful example.
Ontario’s Construction Act requires a holdback to be retained from payments made under a construction contract. The holdback protects the lien rights of subcontractors and suppliers further down the chain.
The holdback is released once the statutory lien period has passed and the Act’s conditions are met. The amount, timing and release mechanics are set by the Act and the contract. Your lawyer advises on how they apply to your project.
Lenders track holdbacks because they affect how much of each advance actually reaches the builder, and when the remainder is paid.
Lien searches
A construction lien registered against title can hold up an advance until it is dealt with. The lender’s lawyer searches before each draw for this reason.
Other provinces have their own lien legislation, with different periods and procedures. Your lawyer will confirm what applies where your project is.
What slows a draw
A missing statutory declaration. A budget variance without an explanation. A lien on title. Insurance that has lapsed or does not match the lender’s requirements. A change order the lender has not seen. Each is avoidable with a checklist and a calendar.
What we do on draws
After commitment, our fulfillment lead carries the file through closing and every draw.
Note
General information only, not legal advice. Holdback and lien rules are set by statute and by your contract, and differ by province. Speak to your lawyer about your project. Every advance is subject to the lender’s approval and the terms of the loan agreement.